Taibilla launches €2.97M replacement of asbestos‑cement ‌pipeline to secure Torrevieja water supply

Fast ⁣summary

  • mancomunidad de Canales del Taibilla (MCT) will invest €2,965,914 to⁤ replace a 2 km section of asbestos‑cement (fibrocemento) pipeline serving Torrevieja.
  • project is 60% co‑financed with ‍European funds and has a 12‑month execution⁢ period.
  • new pipeline will be ⁢ductile‑iron, more than 0.5 m ⁤in diameter,​ to ⁤increase transport capacity and reduce breakdowns.
  • work runs from Los Montesinos industrial estate to La Siesta (torrevieja) and includes special crossings and limited‌ land expropriations.
  • Part ​of a broader MCT ‍investment⁢ plan that includes a €23M Vistabella underground​ reservoir (65,000 m3) to improve storage⁢ for murcia and Alicante areas.

Introduction

Torrevieja – The ‌public water body Mancomunidad de Canales del Taibilla (MCT), dependent on Spain’s Ministry for⁤ the Ecological Transition, has approved a near‑€3⁣ million ‍investment to replace⁢ a critical stretch‍ of​ buried pipeline that supplies potable water to the tourist city of Torrevieja. The work, partially funded by the European Union, targets reliability and capacity improvements in ​a sensitive natural area between the La Mata and ⁣Torrevieja lagoons.

What the project includes

  • Budget: €2,965,914 with 60% financed by EU funds.
  • length: approximately‌ 2 kilometres, between the Los Montesinos industrial ⁣estate and the La ‍Siesta residential area (Torrevieja).
  • Material: replacement of asbestos‑cement (fibrocemento) pipes-installed in ⁤the 1960s/70s-with a ductile‑iron pipeline more than 0.5 m in diameter.
  • execution time: 12 months.
  • Special works: steel pipe jacking (hinca de acero) for the crossing under the CV‑945 regional road and reinstatement of⁣ agricultural services.
  • Expropriations: mainly⁣ temporary,affecting about 10,000 m²⁤ for construction access ⁣and works.

Why the ⁣upgrade is needed

MCT explained the main aim ‍is to increase the ⁤pipeline’s capacity to transport higher flows and reduce frequent breakdowns caused by the heavy demand on that ramal. Although asbestos‑cement pipes have⁤ been prohibited ⁢since ‍2001 ‍in Spain, many of ⁣the supply lines built in the 1960s and 1970s​ remain in service.⁢ The section that brought Taibilla water to Torrevieja‍ was first put into operation in 1972.

The MCT also stressed that continuous,real‑time water quality⁤ monitoring has not detected⁤ contamination issues from the existing asbestos‑cement in normal operational conditions. The risk is associated with material degradation in very specific ⁤situations, which reinforces the prudence of replacing these​ legacy conduits when ⁢undertaking upgrades.

Environmental⁤ context and protected area

The pipeline runs in an area with environmental protection figures ⁤between the‌ two lagoons,La Mata and Torrevieja.The ​project design takes these constraints into account, seeking⁤ to balance infrastructure needs with preservation of the natural habitats that attract tourists and residents alike.

Where this fits into wider‌ MCT investments

This replacement is one of​ many investments MCT is authorising across its‌ distribution network that serves about 80 municipalities in Alicante, the Region of Murcia and Albacete. Recent ⁣approvals include upgrades affecting some thirty towns in the ‍south and center of Alicante province-Alicante city, Elche, crevillent, Santa ⁤Pola-and‍ the 27 municipalities of the Vega Baja.

Vistabella underground reservoir – €23 million project

Alongside pipeline renewals,‍ MCT is reviving the second underground storage tank at Vistabella (Jacarilla). Key facts:

Item Details
Budget €23 million (60% EU ⁢co‑financing)
Capacity 65,000 m³ (same as existing tank)
Location Sierra‌ de Benejúzar‌ – semi‑buried, gravity feed advantage
Purpose Improve regulation and storage for metropolitan Murcia and parts of Alicante

The Vistabella tank project – originally⁣ conceived​ in 2020 and paused due to financing constraints -​ aims to boost the MCT’s ability‌ to‍ buffer peaks in demand or outages, and ​to store desalinated water produced at plants such⁢ as‍ Torrevieja and San Pedro. Although the Torrevieja desalination plant produces sizeable volumes, much of its output​ (around 83 hm³/year) ⁢is currently allocated to irrigation within the Tajo‑Segura transfer community; urban supply from Torrevieja desalination ‌would be preferential only in cases of extreme drought.

Historical background of water supply to⁢ Torrevieja

  • 1972 – First‌ Taibilla ramal started ⁢supplying potable water to Torrevieja.
  • Late 1970s -⁣ Regularisation and expansion of supply took place after the Tajo‑Segura transfer began​ delivering additional water in 1979.
  • 2013 onward – Desalinated water became another meaningful source to cover growing demand.
  • Present – Torrevieja receives about 12 hm³⁤ (hectometres cubed) per year to⁢ meet municipal and tourist needs.

What residents and stakeholders should know

  • Duration: Expect⁣ construction activity lasting up to 12 months. MCT has notified affected⁣ municipalities and will handle scheduled ‍temporary land occupations and some limited expropriations.
  • Service impact: MCT’s plan focuses on minimizing disruptions. Where possible, works will be phased and require road crossing techniques (steel​ jacking)⁣ to reduce interference with‌ traffic and farming⁢ activities.
  • Health and safety: MCT maintains that water quality monitoring shows no present contamination from asbestos‑cement pipes, but replacement is ‌being done to⁢ improve reliability and remove legacy material.
  • Funding: The​ project ⁤is largely EU‑funded, part of the Operational Programme 2021-2027 Feder co‑financing.

Why this matters

Upgrading old ⁣infrastructure is critical for coastal towns like Torrevieja ‍that face ⁣seasonal population spikes and high tourist demand. Replacing aging asbestos‑cement pipelines with modern ductile‑iron mains increases⁢ hydraulic capacity,reduces the frequency of leaks and breaks,and aligns network assets with current⁣ health,safety and environmental standards. Coupled with ⁢new storage capacity at Vistabella, the investments strengthen long‑term water security for residents, agriculture and tourism across the Vega baja and Murcia area.

Timeline and next steps

  1. Approval and ⁤start of public tender (already​ authorised by MCT executive committee).
  2. Expropriation notifications issued to ‌affected landowners; temporary occupations and final permissions to be formalised.
  3. Contract award and mobilisation of construction teams; expected 12‑month work schedule.
  4. Completion, testing and connection‌ to the distribution network; monitoring to ensure increased capacity and‍ reliability.

Keywords

Torrevieja, Mancomunidad de canales del Taibilla, MCT, water supply, pipeline replacement, asbestos‑cement,⁣ fibrocemento, ductile iron, EU funds, Feder, desalination, Vistabella reservoir, La pedrera, tajo‑Segura,‍ Vega Baja, ⁣Los Montesinos, La​ Siesta.


Source ⁢and credits

Share your love